Temporary Roof Scaffold

Date:
Dec 2015

Site:
Solihull M.B.C. Depot, Moat Lane, Solihull

Share:



A complex Temporary Roof design as the scaffold could only be tied to the existing columns and through the widnows to the gable elevations. This was achieved with the aid of flat beams spanning between the columns and windows, and fixed to each scaffold frame between.

An added complication came from the fact that the gable scaffolds had to clear span over the existing lower level roofs. The requirement for 3 lines of beams to both the inside and outside leg lines achieved this requirement.

The temporay roof was constructed using the Hakitec 750 system.