< Back to portfolio

Temporary Roof

Date:
Jan 2012

Site:
Radcliffe Infirmary, Oxford

Share:



58m long x 25m wide x 21m high temporary roof. Tube and fitting scaffolding tied to permanent works for stability, extended and strengthened to support a Haki temporary roof system. Roof was designed to be crane lifted into position for safe erection.

To one elevation, areas available to found the scaffolding were limited so some large bridged sections were incorporated, up to 12m spans supporting the full scaffold and temporary roof above.